How Long Does Roof Replacement Take? Often one working day. The deck under your shingles and the Wiregrass weather decide the rest.

On many Dothan homes, the old roof comes off and the new one is on before supper. Here is what stretches that to two or three days, month by month.

  • 6,000+roofs since 1991
  • 4.9from 100+ Google reviews
  • #30154Alabama HBLB license
MAC crew tearing off old gray shingles, debris on the roof, trees behind
Tear-off underway on a MAC roof replacement in Dothan, AL.
Sample roof weekTypical, not a promise
  1. Mon13
  2. Tue14Day 1Tear-off, dry-in, shingles
  3. Wed15Day 2Ridge, cleanup, walk-through
  4. Thu16Spare day if it rains
  5. Fri17
  6. Sat18
  7. Sun19

Roof replacement, Wiregrass edition

How long does roof replacement take in Dothan, AL? For an asphalt shingle house, usually one to three working days, and many MAC homes are done in one. Rotted decking, extra layers, a steep pitch and summer storms add time. MAC Construction, Alabama license #30154, quotes the days in writing. Call +1 334-726-6401.

  • 1 daymany MAC re-roofs, tear-off to cleanup
  • 13.8July days with measurable rain in Dothan (NOAA)
  • + a few hours to 1 dayfor rotted decking, per GAF

From yes to Day 1

How Long Does Roof Replacement Take Before the Crew Arrives?

The roof day is the short part. Ask how long does roof replacement take from the first call, and most of the answer is lead-up you can check off below.

  1. Free inspection with dated photos

    Stephen or Sam counts the layers and probes for soft decking. You see every photo.

  2. Written quote with a day count

    One price, the material, the tear-off plan and the days we expect.

  3. Permit, where the job needs one

    Inside Dothan city limits, the City permit comes before tear-off.

  4. Material ordered

    Shingles, underlayment, flashing and vents. Made-to-order metal takes longer.

  5. A date, and a backup date

    If a wet front is coming, we move the start with you.

The inspection and photos are free. A formal written roof condition report is a separate paid service; ask for the price when you book.

Ask for a free inspection and a written day count

Form loading. Rather talk? +1 334-726-6401

One real Dothan job

Tear-Off to Ridge Cap: One Dothan Roof in Six Frames

Six photos of one MAC Construction replacement in Dothan, Alabama, in order: a real answer to how long does roof replacement take, frame by frame. Tap to enlarge.

Why the Deck Is Never Left Open

Frames 2 to 4 show the rhythm: strip a section, check the wood, dry it in. Only one section is ever open.

Where the Hours Go

GAF says tear-off to the decking typically takes a few hours. Shingles and ridge fill most of the rest.

How Long Does Roof Replacement Take on This Kind of House?

A single-story house like this is the classic one-day job. Two stories or a cut-up roof add hours.

Interactive planner

Roof Day Planner: How Long Does Roof Replacement Take on Your House?

Set your roof and the month. The planner draws a typical schedule from GAF and IKO ranges, our job notes and NOAA's Dothan rain days. A sketch, not a promise.

Layers to tear off

Pitch

Decking

Material

Typical schedule

1 working dayTear-off, dry-in, shingles and cleanup fit in one day.

  • Tear-off
  • Deck repair
  • Dry-in
  • New roof
  • Cleanup
  • Spare day

October: Dothan averages 7.0 days with measurable rain, about 23% of days.

Mild highs near 81°F; no special temperature steps expected.

Typical ranges only. How long does roof replacement take on your roof exactly? The free inspection sets that number.

The delay ledger

What Adds Time to a Roof Replacement in Dothan, AL

Delays come from three places: what is under the shingles, the shape of the roof and the weather. Only the weather stays a surprise.

How long does roof replacement take when these turn up? Effects from GAF, panel makers and our job notes
What turns upTypical effectSourceKnown before Day 1?
Rotted or soft deckingA few hours to an extra dayGAFPartly
A second or third layerOften about half a day moreOur job notesYes
Pitch over 8/12Slower pace, safety gearGAFYes
Many valleys, dormers and pipesMore cutting and flashingGAFYes
Poor attic ventilationTime to add ventsGAFYes
Tight access, fences, landscapingSetup hours up frontGAFYes
Afternoon stormDry in, return next dry dayGAFForecast only
Frost or a cold snapLater start, hand-sealingGAF bulletin R-133Forecast only
Made-to-order metal panelsDays to weeks before Day 1AB Martin, Western StatesYes
Tan decking with black felt patches after the shingles came off
Decking right after tear-off in Dothan, AL, before it is checked.
Worker on bare decking with tear-off debris, work truck and van below
Tear-off debris on a Midland City, AL job.

How Long Does Roof Replacement Take When the Decking Is Rotten?

Nobody sees the whole deck until the shingles are off. Soft sheets are photographed, shown to you and replaced at the per-sheet price on your quote. Bernice Anne's review below lists repairs and a chimney removal inside one roof day.

Two Layers Mean Twice the Tear-Off

Dothan enforces the 2021 International Residential Code, and R908.3.1.1 bars new shingles over two existing layers or a wet, rotted roof. Everything comes off, and the extra weight takes time to haul. See our building code guide.

So how long does roof replacement take with a second layer? Often about half a day more on an average house.

The Wiregrass calendar

How Long Does Roof Replacement Take in Alabama's Rainy Summer?

Dothan gets about 54 inches of rain a year, and not evenly. NOAA's 1991-2020 normals for Dothan Regional Airport show how long does roof replacement take to fit around the weather, month by month.

Dothan, AL roofing weather by month: days with 0.01 in. or more of rain, average high and low (NOAA 1991-2020 normals)
MonthRain daysAvg high / lowRoof-day note
January10.562° / 40°FFrost may delay start
February9.966° / 43°FFrost may delay start
March8.873° / 49°FGood roofing weeks
April7.479° / 55°FDriest stretch
May7.987° / 64°FGood roofing weeks
June12.891° / 71°FEarly starts, spare day
July13.893° / 73°FEarly starts, spare day
August13.492° / 72°FEarly starts, spare day
September8.488° / 67°FGood roofing weeks
October7.081° / 57°FDriest stretch
November8.471° / 47°FGood roofing weeks
December10.764° / 42°FFrost may delay start
Low view along a roofline under heavy gray clouds
Heavy clouds over a MAC job (job town not recorded).

Summer: Start Early, Keep a Spare Day

July averages 13.8 rain days and highs above 93°F. Malarkey advises working hot days in the morning, so crews start early and dry in before afternoon storms. How long does roof replacement take in July, then? The same crew days, plus a spare.

Winter: Shingles That Wait for Sun

January lows average under 40°F. GAF says shingles handle best above 40°F and may need hand-sealing in the cold. Frost can delay the start; otherwise, how long does roof replacement take in winter is about the same.

Sources: NOAA U.S. Climate Normals 1991-2020, GAF temperature bulletin, Malarkey cold-weather bulletin and GAF shingle instructions (dry deck rule).

Shingles or metal

Shingle vs Metal: What the Big Guides Say About Install Days

National guides agree on shingles and disagree on metal. Here is how long does roof replacement take by their numbers, on one 14-day scale.

Published install ranges, working days on the roof (permits and ordering not included)
Roof typeWho saysPublished rangeRange bar
Asphalt shinglesGAF blog (2024)1 to 2 days, average-size home
Asphalt shinglesIKO (2026 update)A day or two, start to finish
Asphalt shinglesAngi (Jul 2026)1 to 3 days
Steel sheetsRoofr3 to 4 days
Metal, all typesAngi (Jul 2026)7 to 14 days

How Long Does Roof Replacement Take With Architectural Shingles?

Architectural shingles from TAMKO, CertainTeed, GAF, Owens Corning and Malarkey are most of our work. See our architectural shingle page.

Crew member on blue underlayment with new dark gray shingles started at the top
Shingles start at the top of a dried-in slope in Midland City, AL.
Blue underlayment with ridge-cap bundles staged and a worker on the roof
Ridge-cap bundles staged for the last step, Dothan, AL.

Why Metal Takes Longer, Before and On the Roof

Panels and trim are fitted piece by piece, and standing seam is made to length. AB Martin lists its panels as usually ready 2 to 3 days after an order; Western States Metal Roofing quotes two to three weeks.

We install 3-ft screw-down panels and snap-lock standing seam; see our metal roofing page.

Panel lead times: AB Martin ABSeam panel and Western States Metal Roofing.

Real customers, real clocks

One Day, a Day and a Half, Two and a Half: What Customers Timed

Rated 4.9 from 100+ Google reviews. Three customers, quoted word for word, answer how long does roof replacement take. We don't say where reviewers live.

  1. Google review · 5 out of 5 stars

    "Stephen McDuffie and the crew of MAC CONSTRUCTION got my roof done in one day. Tore off old roof. Did repairs. Removed the old turbines and chimney. … Very responsible priced. I recommend MAC CONSTRUCTION."

    Bernice Anne1 day on the roof
  2. Google review · 5 out of 5 stars

    "I had a roof replacement done. I think they did a great job. …finished in 1 and 1/2 days. So far everything is great. As of today I would recommend them highly."

    Grimm Crowley1½ days on the roof
  3. Google review · 5 out of 5 stars

    "Excellent communication throughout the contracting and installation phases. They were on time and very professional with onsite project management. They completed a complex roof in 2.5 days and it looks great. Exceptional clean up as well. I highly recommend them as a roofing contractor!"

    Bill Roberts2½ days on the roof

Read more MAC Construction reviews

Real experience, real projects

What 6,000+ Roof Days Actually Teach You About Timing

Stephen McDuffie started roofing in 1985 and founded MAC Construction in August 1991. His son Sam works beside him full-time, and the team of 15 has put on 6,000+ roofs.

The lesson is simple: when someone asks how long does roof replacement take, the honest answer starts with a plan. Layers counted, decking probed and material on site make one-day jobs possible.

Workers on bare tan decking during tear-off with an open field behind
Tear-off on a larger roof in Wicksburg, AL.

We are not claiming to be the fastest or best roofer in Dothan. The video shows Stephen and Sam McDuffie during a real MAC Construction roof replacement.

Stephen, in his words: "A great roofer will not cut corners to get a job."

Watch: Real MAC Construction Project Video

Rules that move the start date

Permits, Licenses and Claims: The Paper Side of the Timeline

Paperwork rarely changes how long does roof replacement take on the roof itself. It changes when the crew can start.

City of Dothan

Permit First, Tear-Off Second

Dothan requires permits for alterations under Section 14-5, issued to the owner or a City-licensed contractor, online or at the Civic Center weekdays 8:00 to 4:00. Outside city limits, the county or town decides.

City permit requirements · City permit FAQ · (334) 615-4450

State of Alabama

Licensed Roofer Over $2,500

Residential roofing over $2,500 needs a Home Builders Licensure Board license. Ours is #30154; check any roofer at hblb.alabama.gov or see our license lookup guide.

Insurance claims

Your Claim, Your Pace

Under Ala. Code §8-36-2 a residential roofer cannot negotiate with your insurer for you. We give you dated photos and a written scope. See the Alabama Department of Insurance warning and our claim guide.

Questions

Roof Replacement Timing Questions from Dothan Homeowners

Next steps

Planning a New Roof Somewhere in the Wiregrass

Crews leave West County Road 70 for Dothan, Headland, Ozark and Enterprise. How long does roof replacement take out of town? The same roof days; the drive is planned in.

Free inspection, written day count

Circle a Date. We'll Tell You How Many Days It Takes.

Want to know how long does roof replacement take on your own Dothan, AL house? Send the form and Stephen or Sam will set a time to look.

  1. 1We inspect the roof and take dated photos, free.
  2. 2You get a written quote with the price and the planned days.
  3. 3You pick the date, with a backup. Replacements carry a 5-year written workmanship warranty.